City
Announces Milling and Paving Schedule for September 1-11
The City of Waterbury Engineering
Department is announcing the approximate milling and paving schedule for the
coming week and the following week, weather permitting.
Residents should anticipate traffic
delays and/or detours and are encouraged to consider alternate routes when
possible. Parking will be prohibited on affected streets during working hours,
which are from 7:00 a.m. to 6:00 p.m.,
unless otherwise noted.
Milling
and Paving Schedule
Tuesday, September 1
- Columbia
Boulevard: Concrete ramp installation
- Columbia
Boulevard: Milling
- Anna Avenue:
Paving
Wednesday, September 2
- Columbia
Boulevard: Concrete ramp installation
- Columbia
Boulevard: Milling
- Anna Avenue:
Paving
Thursday, September 3
- Columbia
Boulevard: Concrete ramp installation
- Columbia
Boulevard, Dracut Avenue and Fanning Street: Milling
- Anna Avenue:
Paving
Friday, September 4
- Columbia
Boulevard: Concrete ramp installation
- Garland Street,
Malden Avenue, Wigwam Avenue, Appleton Street and Riverside Street:
Milling
- Anna Avenue and
Hans Avenue: Paving
Tuesday, September 8
- Union Street:
Concrete ramp installation
- Union Street:
Night milling
- Hans Avenue and
Leone Street: Paving
Wednesday, September 9
- Union Street:
Concrete ramp installation
- Union Street:
Night milling
- Highland Street:
Paving
Thursday, September 10
- Union Street:
Concrete ramp installation
- Hans Avenue and
Leone Street: Paving
Friday, September 11
- Windsor Street:
Concrete ramp installation
- Highland Street
and Municipal Road: Paving
All work is weather dependent, and
the schedule is subject to change.
Residents with questions regarding
the milling and paving program may contact the City of Waterbury Engineering
Department at 203-574-6851.
###